地质补勘施工方案

2026/1/27 16:48:52

目 录

1.工程概况 .......................................................................................................................... 2 1.1工程简介 ------------------------------------------------------------------------------------------------------ 2 1.2地面环境情况 ------------------------------------------------------------------------------------------------ 3 1.3地下管线情况 ------------------------------------------------------------------------------------------------ 3 1.4工程地质与水文地质情况 --------------------------------------------------------------------------------- 3 1.5原地质详勘情况 --------------------------------------------------------------------------------------------- 4 2.补充钻探孔布置方案设计 .................................................................................................... 4 2.1 补充钻探的目的 -------------------------------------------------------------------------------------------- 4 2.2 补充钻探技术要求 ----------------------------------------------------------------------------------------- 4 2.3 补充钻探孔布置方式及深度控制 ----------------------------------------------------------------------- 5 2.3.1 补充钻探孔布置原则 .......................................................................................................... 5 2.3.2 补充钻探孔布置方式 .......................................................................................................... 5 2.3.3 补钻探测到孤石后的周边加密钻孔 .................................................................................. 7 2.3.4 补充钻探孔的深度设计 ...................................................................................................... 7 3.补充钻探实施方案 .............................................................................................................. 8 3.1 勘察单位 ----------------------------------------------------------------------------------------------------- 8 3.2 补充钻探钻孔数量及位置的选定 ----------------------------------------------------------------------- 8 3.2.1 重点探测区钻孔数量及位置的选定 .................................................................................. 8 3.2.2 矿山法施工段钻孔数量及位置的选定 ............................................................................ 10 3.2.3 盾构进出洞端头钻孔数量及位置的选定 ........................................................................ 10 3.2.4 联络通道钻孔数量及位置的选定 .................................................................................... 10 3.2.5 其他区域钻孔数量及位置的选定 .................................................................................... 11 3.3补充勘察的方法及流程 ---------------------------------------------------------------------------------- 11 3.4补充勘察方案及技术要求 ------------------------------------------------------------------------------- 11 3.4.1钻探 ..................................................................................................................................... 11

地质补充钻探施工方案 3.4.2原位测试 ............................................................................................................................. 14 3.4.3室内试验 ............................................................................................................................. 14 3.4.4 资料整理及勘察报告编写 ................................................................................................ 14 4.施工部署及工期安排 ........................................................................................................ 15 5. 安全文明保证措施 .......................................................................................................... 15 5.1安全保证措施 ---------------------------------------------------------------------------------------------- 15 5.2文明施工保证措施 ---------------------------------------------------------------------------------------- 16 6. 应急预案 ........................................................................................................................ 17

1

地质补充钻探施工方案 1.工程概况

1.1工程简介

广州市轨道交通六号线二期工程【施工六标】土建施工项目位于广州市萝岗区,线路西起于暹岗站东端头,沿开创大道向东行进,并转至路北穿越萝岗站后,沿开创大道向东前行,下穿北二环高架桥后,转向开创大道路南,下穿隔坡涌后再转至开创大道路中,最后进入香雪站西端头。本标段工程线路位置见图1.1-1所示。

图1.1-1 本标段工程线路示意图

92.49m暹岗站萝岗站香雪站车辆段出入线段线 图1.1-2 本标段工程范围示意图

本标段工程包括两个盾构区间、一座车站、一个出入段线明挖区间、一个中间风井和多个附属工程,其中【暹岗站~萝岗站】盾构区间左线隧道包含一段矿山法+盾构空推拼装管片通过的隧道。见图1.1-2所示。

2

地质补充钻探施工方案 两个盾构区间隧道双线总长5768.797m(包括矿山法段),采用四台盾构机施工,其中两台盾构机在萝岗站西端头始发向暹岗站掘进,两台盾构机在萝岗站东端头始发向香雪站掘进。

本地质补充钻探方案主要考虑盾构区间隧道施工。 1.2地面环境情况

本标段区间隧道基本在开创大道及绿化带下方穿行。开创大道路面现状宽约60m,双向八车道布置,地面车流量较小,路南北两侧建筑物较少,场地开阔。隧道主要旁穿高压电塔、保利香雪园、北二环高速桥桩基、大塱村民宅等建筑物,下穿地下通道U型槽口部、广州国际体育演艺中心前广场、暗渠、机场输油管道等。

本区域为丘陵地貌,沿线为剥蚀残丘和丘间冲沟相间,因道路等工程建设,原地貌大多经过挖填。根据目前地貌及现场调查,本标段线路主要旁经四座山丘,分别位于暹岗站附近、暹萝区间1#联络通道(YDK38+686)附近、萝岗站前后、萝香区间1#联络通道(YDK40+020)附近。山丘及附近地表遍布球状风化核。 1.3地下管线情况

本标段盾构区间地面管线主要集中在道路南、北两侧,在隧道投影范围内的管线主要有:Φ150给水塑料管、Φ1000给水钢管、Φ219的输油管(钢管),Φ1600的砼污水管以及Φ325煤气管(钢管)。

1.4工程地质与水文地质情况

本标段盾构区间隧道埋深15~24m。地层从上至下主要有填土层、砂层(主要为中粗砂)、花岗岩残积土层、花岗岩全、强风化带。隧道穿越的地层主要有<3-2>中粗砂层、<4N-2>粘土层、<5H-2>花岗岩残积土层,局部穿越<6H>花岗岩全风化层。其中<5H-2>花岗岩残积土在水平方向上分布广泛,在垂直方向上分布严重不均。

根据地区经验,硬塑状的花岗岩残积土层、坚硬土状的全风化花岗岩、半岩半土状的强风化花岗岩中容易发育球状风化孤石。而根据详勘报告,本标段盾构隧道洞身范围内揭露有孤石存在。孤石容易导致盾构机刀具失效和磨损严重,甚至造成刀盘损坏,对盾构施工危害极大。因此,施工前,应对隧道通过地层情况进行详细调查,以便采取相应的处理措施,尤其是对孤石的处理,确保盾构掘进的可靠性。这是编制本方案的主要目的。

地下水按赋存方式分为第四系松散土层孔隙水,块状基岩裂隙水。本标段详勘所揭露的地下水水位埋藏变化较大,稳定水位埋深为0.60~10.80m,平均埋深为3.63m。

3


地质补勘施工方案.doc 将本文的Word文档下载到电脑
搜索更多关于: 地质补勘施工方案 的文档
相关推荐
相关阅读
× 游客快捷下载通道(下载后可以自由复制和排版)

下载本文档需要支付 10

支付方式:

开通VIP包月会员 特价:29元/月

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信:xuecool-com QQ:370150219