工程建设监理工作报告(单位工程验收)

2026/1/12 2:40:24

中山市东河水利枢纽工程 (水闸、船闸、泵站单位工程验收)

工程建设监理工作报告

GP DI 广东省科源工程监理咨询公司

中山市东河水利枢纽工程建设监理部

二○○一年六月

中山市东河水利枢纽工程 (水闸、船闸、泵站单位工程验收)

工程建设监理工作报告

审核:

编写:

GP DI 广东省科源工程监理咨询公司

中山市东河水利枢纽工程建设监理部

二○○一年六月

目 录

1.工程概况 ························ 1

1.1地理位置、建设规模、内容及效益 ····················································· 1 1.2主要工程量及费用 ·········································································· 1 1.3计划工期 ······················································································ 2

2.监理规划 ························ 2

2.1项目结构图 ··················································································· 2 2.2项目总目标 ··················································································· 2

3.项目实施的组织 ····················· 2

3.1建设单位 ······················································································ 2 3.2监理单位 ······················································································ 3 3.3设计单位 ······················································································ 3 3.4土建及金属结构制作、安装单位 ························································ 3 3.5机电设备安装单位 ·········································································· 4 3.6质量监督单位 ················································································ 4

4.监理组织机构 ······················ 4

4.1监理单位 ······················································································ 4 4.2监理部组织结构图 ·········································································· 4 4.3监理制度 ······················································································ 5

5.监理过程 ························ 5

5.1质量控制 ······················································································ 5 5.2进度控制 ······················································································ 6 5.3投资控制 ······················································································ 6 5.4合同管理 ······················································································ 8 5.5信息管理 ······················································································ 8 5.6协调工作 ······················································································ 9

6.监理效果 ························ 9

6.1质量 ···························································································· 9 6.2进度 ··························································································· 18 6.3投资 ··························································································· 19

7.经验与建议 ······················· 19 8.附件 ·························· 20

8.1监理机构的设置与主要工作人员情况表。 ··········································· 20

8.2工程建设监理大事记 ····················································· 20

1.工程概况

1.1地理位置、建设规模、内容及效益

中山市东河水利枢纽工程位于中山市岐江河东河口,下连横门水道,是中顺大围(广东省十大联围之一)最大、最重要的水利工程,属大(二)型工程,也是中山市建国以来最大的单项水利工程。保护范围709平方公里(包括中山市城区),捍卫耕地51万亩、人口70余万及超过1000亿元固定资产。

枢纽工程包括水闸、船闸和泵站各一座以及生产、生活管理区,其中水闸总净宽150米,分10孔(旧水闸总净宽160米32孔),设计最大过闸流量为每秒1020立方米;船闸按内河Ⅳ级航道、通航500吨级设计,闸首净宽16米,船室长120米,设计年通航量1000万吨;泵站设计流量为每秒273立方米,单机容量180010800千瓦,总装机容量10800千瓦,安装叶轮直径3240毫米立式轴流泵6台,采用1万伏直配线供电。

工程建成运行后,主要具有五大效益:一是防洪、防台风暴潮效益,防洪标准由原不足50年一遇提高到100年一遇,防潮标准达100年一遇暴潮水位加10级风浪爬高要求;二是排涝效益,确保围内10年一遇24小时暴雨不成涝;三是环保效益,通过合理调度,促使围内河涌水流动,强化河道自净功能,从而改善环境;四是灌溉效益,新工程注入围内的新鲜水量大幅度增加,有利于农业生产;五是航运效益,船闸按Ⅳ级航道500吨级标准设计,船闸闸首由13米扩宽为16米,改建后航道更为顺直,从根本上改善通航条件。

1.2主要工程量及费用

本工程土建工程量为土方45万立方米,石方4.64万立方米,混凝土5.3万立方米。耗用水泥3万吨,钢材0.93万吨。总工程费用20010.4万元,其中水闸7436万元,船闸3048万元,泵站9526.4万元。


工程建设监理工作报告(单位工程验收).doc 将本文的Word文档下载到电脑
搜索更多关于: 工程建设监理工作报告(单位工程验收) 的文档
相关推荐
相关阅读
× 游客快捷下载通道(下载后可以自由复制和排版)

下载本文档需要支付 10

支付方式:

开通VIP包月会员 特价:29元/月

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信:xuecool-com QQ:370150219