正文科技股份有限公司
文件名稱(Doc Name)
Product Transfer Operation Procedure
文件編號(Doc No)版? 次(Version)生效日期
(Effective Date)
QP0413 1.0 2005/12/28
文件制、修訂申請(審核)電子會簽單 (Document Preparation、Revision Application [Review] E-countersign Form ) 修 訂 一 覽 表(Revision List) 修定日期 版本 (Revision Date)(Version)2005/12/26 1.0 修 訂 內 容 (Revision Content)initial release 機種移轉作業程序, 英文發行 備 註 (Remark)附加檔案 * (Attachment)QP0413.10 Product Transfer Operation Procedure.doc 三階支援文件 :(The Third Stage Support Document)項次 單?位?名?稱 (Item)(Department)
147101316
分發數量 項次 單?位?名?稱
(Issued Qty)(Item)(Department)
2
分發數量 項次單?位?名?稱
(Issued Qty)(Item)(Department) 3
分發數量
(Issued Qty)
58111417
69121518
四階表單:(The Fourth Stage Form)?記錄保管年限:? ?(preservation period of record)
?記錄保管單位:? ?(preservation department of record)
姓名 (Name)
楊文誠 蘇暉皓 * 林添進 *
單位 (Department)
正文-品保部 正鵬-品保處 生產處
姓名 (Name)
單位 (Department)
?制定(申請)
?(Preparation[Application])?審查 (Review)
?核准 (Approval)QR0501.11B
Gemtek Technology Co., Ltd.Procedure Document
Product Transfer Operation Procedure
Doc. No. QP0413
Edition 1.0 Page Effective Date
1/7
Doc. Name
205/12/28
Document Revision History Record
Item Revision Date Edition Page Revision Content 1 2005/04/13 1.0 Initial Release
Remark QR0501.12A
Gemtek Technology Co., Ltd.Procedure Document
Product Transfer Operation Procedure
Doc. No. QP0413
Edition 1.0 Page Effective Date
2/7
Doc. Name
2005/12/28
1. Purpose:
To standardize technical transfer operation from Head Office (Gemtek Technology) to KS/SZ, and to
clearly define relevant unit responsibility respectively so as to ensure successful transfer of new
models.
2. Scope:
Applies to all models that are transferred from Head Office but never produced in KS/SZ.
3. Definition:
3.1 Gemtek: Head Office of Gemtek Technology 3.2 KS: Gemtek KS 3.3 SZ: Gemtek SZ
4. Authority/ Responsibility:
4.1 Gemtek PM: As the contact window of Head Office, responsible for coordinating internal issues
concerning relevant documents/ technique transfer and schedule control.
4.2 Gemtek DCC: Responsible for issuing relevant documents needed by model transfer to KS/SZ DCC.
4.3 Gemtek MMD: Responsible for material transfer schedule and document application for KS/SZ
4.4 Gemtek Production Technology Section: Responsible for transfer operation of models that have
been mass produced in Gemtek, including assisting test equipment setup in KS/SZ, solving abnormalities in PVT, receiving PVT Report
from PM (Gemtek), confirming PVT results and feeding back to PM (Gemtek).
4.5 Gemtek ET Dept.: Responsible for transfer operation of models that have PVT but not mass
produced in Gemtek or that never have been mass produced in Gemtek,
including assisting test equipment installation in KS/SZ, solving abnormalities in PVT, receiving PVT Report from PM (Gemtek), confirming PVT results and feeding back to PM (Gemtek).
4.6 Gemtek R&D Dept.: Responsible for EVT operation of new models in KS/SZ, including assisting
test equipment installation in KS/SZ, solving abnormalities in PVT, receiving
PVT Report from PM (Gemtek), confirming PVT results and feeding back to
QR0501.05A
Gemtek Technology Co., Ltd.Procedure Document
Product Transfer Operation Procedure
PM (Gemtek).
Doc. No. QP0413
Edition 1.0 Page Effective Date
3/7
Doc. Name
2005/12/28
4.7 Gemtek IE of MFG: Responsible for throughput evaluation and production/test equipment transfer 4.8 KS/SZ Sales (PM): As contact window of KS/SZ, responsible for coordinating internal issues
concerning relevant documents/ technique receipt and schedule control. 4.9 KS/SZ DCC: Responsible for receiving relevant documents from Gemtek DCC for transferred
models.
4.10 KS/SZ Engineering Dept.: Responsible for setting up test equipments, confirming packing
material design, approving sample and providing PM KS/SZ with PVT Report and
*.LOG files recorded after test in SFCS and Program.
5. Operation: 5.1 Operating Process Flow Chart KS/SZ PM follow up SMT preparation pre A PVT KS/SZ PM release PVT application Receive documents and prepare PVT New Model Transfer Notice Content PM will release “New Model Transfer Notice” (including time for PVT and mass Document & Sample Responsible UnitGemtek PM KS/SZ PM Gemtek MMD Gemtek DCC KS/SZ DCC Gemtek IE Gemtek PM KS/SZ PM Notice When new model transfer is needed, Gemtek New Model Transfer production, forecast, PVT purpose, etc.) and material ready date documents or sample 1. DCC in KS/SZ receives documents from Refer to 5.2.2, 21 Gemtek DCC. Detailed items refer to 5.2.2 2. Throughput evaluation 1. KS/SZ PM release “PVT Application Form” 2. Check if all documents are ready Check if everything is ready in SMT pre PVT (stencil, program, carrier, parameter setting) Production/ test equipment transfer PVT Application Form 2. Check List 1. PVT Application Form KS/SZ PM KS/SZ MFG Gemtek IE QR0501.05A