5.2 Construction Schedule

East-west Gas Pipeline Project Construction Procedure for Cleaning, Gauging And Hydro testing of Pipelines Rev.: A1 China Petroleum Pipeline Bureau(CPP) Document No.: EWPL00-COS-PR-0014 For detailed information about the construction schedule, please refer to Construction Execution Plan

6.0 PIPELINE SECTION CLEANING AND GAUGING

6.1 General

Pipeline section cleaning and gauging activities are carried out after pipeline welding and backfilling and before hydrostatic testing. Pipeline cleaning is provided to remove any large debris left inside the pipeline after the welding, while gauging inspection is conducted to identify the extent of any out-of roundness, buckles, dents or other deformation in the pipelines.

The length of cleaning/gauging section basically will be the distance between two line valve stations or a line valve station and the nearby pig trap station. Compressed air will be used as propelling medium for pipeline pigging and gauging.

6.2 Preparations for Cleaning and Gauging 6.2.1 Site Layout

Layout of the Construction Site

The arrangement of the main equipment and devices involved in the operations of section cleaning and gauging is shown in Sketch-1 below.

Main equipment and devices for pigging:

? The Capacity of Compressed Air: 160 m/min.

? Temporary pig traps: launchers and receivers for the pipeline of 48”

3

Page 13 of 56

East-west Gas Pipeline Project Construction Procedure for Cleaning, Gauging And Hydro testing of Pipelines Rev.: A1 China Petroleum Pipeline Bureau(CPP) Document No.: EWPL00-COS-PR-0014

Before section cleaning operation pits shall be excavated at the both ends of the pipeline section for the installation of temporary launcher and receiver traps, and for the pig launching and receiving. 6.2.2 Cleaning pig

The pig shown as below will be used for pipeline sections for cleaning. Cleaning pigs will be equipped with 4 urethane cups, 2 nylon wire brushes and 4 spacers.

Page 14 of 56

East-west Gas Pipeline Project Construction Procedure for Cleaning, Gauging And Hydro testing of Pipelines Rev.: A1 China Petroleum Pipeline Bureau(CPP) Document No.: EWPL00-COS-PR-0014

Figure-2

6.2.3 Gauging pig

The sketch shown as below is the pig used for pipeline sections gauging inspection. Gauging pigs will be equipped with 4 urethane cups, 4 spacers and an aluminum gauging disc.

Page 15 of 56

East-west Gas Pipeline Project Construction Procedure for Cleaning, Gauging And Hydro testing of Pipelines Rev.: A1 China Petroleum Pipeline Bureau(CPP) Document No.: EWPL00-COS-PR-0014

Figure-3

The diameter of the gauging disk is 95% of the minimum internal diameter of the pipeline section. The thickness of the disks is10mm and the disk shall be made with radial incision at interval of 45°.

Before sending the gauging pigs, Reference marks shall be made to them witnessed by both the Engineer-in-Charge and CONTRACTOR?s test engineer. Reference marks as

Diameter of the Disc: ____ Date & Time: ____ Engineer-in-Charge: ____ CONTRACTOR’s Test Engineer: ____

shall be made by water-resistant paint.

6.2.4 Installation of the equipment and devices for cleaning & gauging pigging Main equipment and devices for pigging:

? ?

The capacity of supply compressed air: 90 m/min~ 160m/min. Temporary pig traps: launchers and receivers for the pipeline of 48”.

Page 16 of 56

3

3


Procedure for Cleaning,Flushing,Gauging an.doc 将本文的Word文档下载到电脑
搜索更多关于: Procedure for Cleaning,Flushin 的文档
相关推荐
相关阅读
× 游客快捷下载通道(下载后可以自由复制和排版)

下载本文档需要支付 10

支付方式:

开通VIP包月会员 特价:29元/月

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信:xuecool-com QQ:370150219